Factors Affecting Delayed Implementation of Railway Station Projects: Case Studies in Indonesia
이용수 43
- 영문명
- 발행기관
- People & Global Business Association
- 저자명
- Syaeful Karim Wisnu Isvara Mohammad Ichsan
- 간행물 정보
- 『Global Business and Finance Review』Vol.29 No.11, 46~60쪽, 전체 15쪽
- 주제분류
- 경제경영 > 경영학
- 파일형태
- 발행일자
- 2024.12.31

국문 초록
Purpose: This research aims to identify risk indicators of delays in critical scheduling activities of a railway station construction project from the service provider's perspective. It aims to help prepare and respond to potential delays, ensuring project success and boosting economic growth and national connectivity in Indonesia.
Design/methodology/approach: A literature study was conducted to identify variable risk information on project delays in a railway station project. Expert validation was done using Delphi methods or structured interviews. Focus group discussion (FGD) was used to identify the most dominant risks in each critical scheduling activity. The study revealed 51 risk variables influencing project delays, with 22 dominant risks identified in a case study project. FGD surveys were conducted on each critical activity, and data from five experts was evaluated using descriptive techniques and elimination techniques to determine the most influential risk. The results were that there were 9 critical activities and 6 most dominant risks.
Findings: The study reveals that delays in completing the railway station project are primarily due to issues with issuing permits, which is the most significant risk factor for the three critical activities. Other risks include working on the active track, adjusting train operation patterns, dependencies between phases and work packages, long decision- making processes by the project owner, and complicated construction authorization procedures.
Research limitations/implications: Further comprehensive investigation is required to ascertain the impact of project risk assessment on the expenses and caliber of additional railway projects, in addition to projects with broader scopes like other transportation construction projects.
Originality/value: This study analyzes and identifies the most dominant risks to critical activities of railway station projects, and investigates their impact on project completion time optimization.
영문 초록
목차
Ⅰ. Introduction
Ⅱ. Literature Review
Ⅲ. Materials and Method
Ⅳ. Discussion
Ⅴ. Conclusions, Limitations, and Future Research
Funding Statement
Conflicts of Interest
References
해당간행물 수록 논문
참고문헌
- Global Business & Finance Review
- Civil Engineering Dimension
- Sustainability
- International Journal of Innovative Research in Science, Engineering and Technology
- International Journal of Project Management
- Expert Systems with Applications
- IOP Conference Series: Earth and Environmental Science
- Journal of Research in Infrastructure Designing
- Global Business and Finance Review
- Procedia Engineering
- IOP Conference Series: Earth and Environmental Science
- Technology, and Sciences (ASRJETS) American Scientific Research Journal for Engineering
- Oxford Review of Economic Policy
- Journal of Construction Engineering and Management
- Innovative Infrastructure Solutions
- Innovative Infrastructure Solutions
- Innovative Infrastructure Solutions
- Procedia Engineering
- Journal of Management in Engineering
- European Journal of Environmental and Civil Engineering
- IEEE Transactions on Engineering Management
- Journal of Construction Engineering and Management
- Global Business and Finance Review
- Global Business and Finance Review
- IOP Conference Series: Materials Science and Engineering
- IOP Conference Series: Materials Science and Engineering
- Periodicals of Engineering and Natural Sciences
- International Journal of Sustainable Construction Engineering and Technology
- Buildings
- Sustainability
- Journal of Construction Engineering and Management
- Acta Polytechnica Hungarica
- International Journal of Students' Research in Technology Management
- Sustainability
- Sustainability (Switzerland)
- Global Business and Finance Review
- International Research Journal of Engineering and Technology
- Construction Economics and Building
- Journal of Civil Engineering and Infrastructure Technology
- AIP Conference Proceedings
- International Journal of Civil Engineering and Technology
- Journal of Engineering and Advanced Technology (IJEAT)
- Journal of Property Investment and Finance
- Kemenkeu
- International Journal of Construction Management
- Journal of Public Policy and Management Review
- Indonesian Journal of Construction Engineering and Sustainable Development (Cesd)
- Padjadjaran Journal of International Relations
- Advances in Civil Engineering
최근 이용한 논문
교보eBook 첫 방문을 환영 합니다!
신규가입 혜택 지급이 완료 되었습니다.
바로 사용 가능한 교보e캐시 1,000원 (유효기간 7일)
지금 바로 교보eBook의 다양한 콘텐츠를 이용해 보세요!